Projects

Last projects


CONSTRUCTION OF SHAMAKHI – PIRGULU ROAD

Construction of 12,5 km 2 lane road and 2 nos. bridges with the total length of 84 m.

CONSTRUCTION OF GUSAR – ENIG – LAZA – SUVAR ROAD

Construction of 38 km 4 lane road and 3 nos. bridges with the length of 65 m, 73 m and 88 m.

CONSTRUCTION OF SHEMKIR – GEDEBEY ROAD

Construction of 22,5 km 2 lane road and three spans bridge with the length of 53 m.

2012 – 2015

129 886 667,52 USD

Length 108 km

CONSTRUCTION OF AGSU – KURDAMIR - IMISHLI ROAD

Construction of 108 km of road and 4 bridges with the total length of 766 m.


The scope of works include but not limited:

  • earthworks 2 449 427.00 m3;
  • subbase 242 439.00 m3;
  • base 72 660.00 m3;
  • asphalt-bitumen hot mix 68 080.00 m3;